BWMS Retrofitting for MT MARITIME JINGAN & MT MARITIME NORDIC
Release Time:
2018-07-12
In April and May, Greentec completed parts of BWMS installation work for MT MARITIME JINGAN and MT MARITIME NORDIC from MSI Ship Management Pte Ltd during vessels’ dry-docking at Chengxi Shipyard (Xinrong).
In April and May, Greentec completed parts of BWMS installation work for MT MARITIME JINGAN and MT MARITIME NORDIC from MSI Ship Management Pte Ltd during vessels’ dry-docking at Chengxi Shipyard (Xinrong). This project includes positioning and installation of BWMS equipment foundation, cable arrangement, valve installation and piping installation.
Due to the overloaded production schedule of BWMS maker SUNRUI, the equipment supply was not available during this docking time. As planned together with ship owner, the remaining installation work including equipment installation, piping and cable connection, BWMS commissioning and function test will be completed accordingly when the equipment is ready which is by the end of Sep this year.